What Should You Lay as a Foundation to a Drive?
Whatever drive finish you decide on, the base you lay should essentially be the same: ideally 100-150mm of hardcore. The most efficient method is to use machines to spread and tamp hardcore — digger buckets are particularly effective tampers.
It is very useful to have hardcore laid as early as possible on a building job as it aids access and stops the site becoming a quagmire, but drain-laying timetables do not always allow this use of machinery. Whether it is worth getting machinery in later just to lay hardcore depends on the driveway’s size.